When a Nigerian developer misses an off-plan handover date, your first tool is the contract: its grace period, delay compensation, and right to terminate and get a refund. Put the default in writing, then use mediation; in Lagos, the LASRERA Law 2022 lets the regulator receive complaints and appoint a mediator, and the Citizens' Mediation Centre mediates land and commercial disputes free. Court is the last step. From the US you act through a Nigerian lawyer under a specific power of attorney, ideally together with other buyers in the same project.
Off-plan delays are common, and not always a sign of bad faith: materials prices, approvals and cash flow all slip. What matters to a buyer in Atlanta or Dallas is knowing what you can demand, from whom, and how to apply pressure without flying home. This guide sets out the options in the order most lawyers would use them. It is information, not legal advice.
Start with the contract
| Clause | What it may give you |
|---|---|
| Handover date and grace period | The date from which the developer is in default |
| Delay compensation | A fixed sum or rate per month of delay, or rent for alternative housing |
| Termination right | Your right to end the contract after a set delay |
| Refund terms | How much comes back, in which currency, and how fast |
| Force majeure | Events the developer can rely on to excuse delay; read its scope |
| Dispute clause | Mediation, arbitration or a named court, and the governing law |
If the contract is silent on compensation, you may still have a claim for breach, but its size and success are for your lawyer to judge. If the price was in dollars, check the refund currency; see paying a developer in USD.
The steps, in order
- Gather evidence. Contract, payment receipts, every message about dates, and dated photographs of the site taken by someone you trust.
- Formal demand. Your lawyer writes to the developer's registered address stating the default and what you want: a new firm date with compensation, or termination and refund.
- Mediation. In Lagos, the Citizens' Mediation Centre of the Ministry of Justice handles land and commercial disputes free and records agreements as an enforceable memorandum. Its head office is in Alausa, Ikeja.
- The regulator (Lagos). Under the LASRERA Law 2022, as Mondaq's analysis sets out, the Authority receives and investigates complaints, can appoint a mediator, and can set up a committee of inquiry that gives the developer two weeks to respond. A mediated agreement becomes enforceable once endorsed by a magistrate or judge. LASRERA's website has a "Lodge a Complaint" route.
- Court or arbitration. For breach of contract and refund, as your contract's dispute clause directs.
Choosing between waiting and leaving
The hardest decision is whether to accept a new date or terminate. Waiting keeps you in a project that may still deliver a home at an old price; leaving turns your claim into a refund you then have to collect. Look at evidence rather than promises: is work visibly continuing on site, month by month? Are other buyers being handed units in earlier phases? Has the developer paid any compensation it owes? A developer that is building slowly but steadily is a different risk from one whose site has been quiet for a year. If you accept a new date, put it in a signed variation that keeps your termination right if the new date is missed, and that states the compensation for the period already lost. If you terminate, make sure the refund has a deadline and that your lawyer is ready to act if it passes.
Abandoned projects
Where a project has stopped altogether, the LASRERA Law has provisions on abandoned buildings: completion notices of three months followed by a further three, possible revocation of the right of occupancy, and compensation under the Land Use Act, according to the same analysis. Revocation can hurt buyers too, so take legal advice before pushing the state to act on a project you have paid into.
Acting from the US
- Power of attorney. Give your lawyer, or a relative working with the lawyer, a specific power to negotiate, attend mediation and sign a settlement. See using a power of attorney and, for signing it here, making a Nigerian power of attorney valid from the US.
- Group action. Other buyers in the same project share the problem. A buyers' group with one lawyer costs each member less and carries more weight.
- Keep payments paused. If further stage payments are due, take advice before stopping them: stopping can put you in breach if the contract ties payments to dates rather than stages.
A worked example
Example only. Ngozi in Atlanta paid ₦45,000,000 of a ₦60,000,000 Lagos flat. The contract promised handover in March, a three-month grace period, and compensation of 1% of sums paid for each month of delay after grace, with a right to terminate after twelve months. By October, four months past grace, compensation is 4 × 1% × ₦45,000,000 = ₦1,800,000. Her lawyer's demand letter asks for a new date and that sum. The developer offers a December date and a ₦1,800,000 credit against the final payment, which Ngozi accepts in a signed settlement, keeping her right to terminate if December slips.
Where Pryme fits
A dispute is won on records. Pryme lets you generate verifiable receipts and statements through VerifyDoc.ai, which a lawyer, mediator or court can check are unaltered. A Pryme account opened from the US also holds naira and dollars, so a refund can be received in the currency it is paid.
Questions people ask
What can I do if my developer misses the handover date?
Check the contract for grace period, compensation and termination, send a formal demand through a lawyer, then use mediation, the Lagos regulator for Lagos projects, and finally court.
Can LASRERA help with a delayed off-plan project?
The LASRERA Law 2022 lets the Authority receive and investigate complaints, appoint a mediator and set up a committee of inquiry. Its website has a complaints route.
Can I stop paying a developer who is late?
Take legal advice first. If your contract ties payments to dates rather than construction stages, stopping could put you in breach.
How do I pursue a Nigerian developer while living in the US?
Through a Nigerian lawyer acting under a specific power of attorney, ideally with other buyers in the same project.
Sources
- Mondaq (Famsville): Analysis of the Lagos State Real Estate Regulatory Authority Law 2022 (30 May 2022) · accessed Oct 2026
- Lagos State Real Estate Regulatory Authority (LASRERA): website · accessed Oct 2026
- Lagos State Ministry of Justice: Citizens' Mediation Centre · accessed Oct 2026
- Land Use Act, Cap L5 LFN 2004 (PLAC) · accessed Oct 2026
This article is general information, not financial, legal or tax advice. Products described are provided under the terms on this site and are subject to regulation and eligibility.