When you build in Nigeria from the US, pay in stages tied to finished work, not in advance: agree a priced bill of quantities, release each payment only when the stage is verified by someone independent of the builder (ideally a quantity surveyor registered with QSRBN), and get dated photos, materials receipts and a written acknowledgement for every payment. Keep a retention back until completion and pay into a business account, never cash to an individual.
Why stage payments go wrong from abroad
Most losses follow the same pattern. The builder asks for a large sum to "buy materials before prices rise", photos arrive of blocks that may be on someone else's site, and the next request comes before the last stage is finished. From the US you cannot walk the site, so the payment structure has to do the checking for you.
Set up the project before the first payment
- Get approved plans. In the FCT, for example, the development control department says plans must be prepared by registered town planners, architects and engineers bearing their seals, and that the approved plan and development permit must be kept on site. Each state has its own planning authority and rules.
- Commission a bill of quantities (BOQ): every item priced, so stage costs can be checked line by line.
- Sign a written contract that lists the stages, what "complete" means for each, the price, the timetable and what happens if work is late or defective.
- Appoint an independent checker. The Quantity Surveyors (Registration, etc.) Act makes it an offence for an unregistered person to practise as a quantity surveyor for reward, and QSRBN keeps the register, so ask for the registration number and check it.
- Open a dedicated account for the project so every naira in and out is visible.
A stage plan you can adapt
The percentages below are an example for a ₦60,000,000 bungalow, not an industry standard. Agree your own with the builder and QS.
| Stage | Example share | Example amount | Release when |
|---|---|---|---|
| Mobilisation | 10% | ₦6,000,000 | Contract signed, site set out, insurance in place |
| Foundation to damp-proof course | 20% | ₦12,000,000 | QS confirms foundation and DPC complete |
| Walls to lintel | 20% | ₦12,000,000 | Walls up to lintel, columns cast |
| Roofing | 20% | ₦12,000,000 | Roof covered, verified on site |
| Finishes, services | 20% | ₦12,000,000 | Plaster, wiring, plumbing, windows done |
| Retention | 10% | ₦6,000,000 | Released after a defects period |
Check: 10 + 20 + 20 + 20 + 20 + 10 = 100%, and ₦6m + 4 × ₦12m + ₦6m = ₦60m. Holding back the retention gives the builder a reason to come back and fix defects.
What proof to ask for at each stage
- A QS valuation or site report stating what is complete and what it is worth against the BOQ.
- Dated, geotagged photos and a short live video call walking the site, with a reference point you know, such as a neighbour's gate.
- Receipts for major materials, matched to BOQ quantities.
- A signed acknowledgement for each payment, stating the stage and amount.
- For any variation, a written change order with the price agreed before work starts.
Materials prices move
Builders often justify advance payments by price rises. Prices do move: Legit.ng reported cement at ₦12,000 per 50kg bag from major makers in early September 2026, with July retail ranges of ₦12,500 to ₦15,000 in several cities. Rather than pay months ahead, agree in the contract how price changes are handled, or buy major materials yourself for delivery to site, with receipts in your name.
Red flags
- Requests to pay into a personal account or a relative's account.
- A new request before the QS has signed off the current stage.
- Photos without dates, or that do not match the plan.
- Resistance to an independent check.
- Large "materials" sums with no supplier receipts.
A monthly routine that keeps you in control
Distance turns small problems into large ones because nobody tells you early. A fixed routine fixes that. Each month, ask for the same pack: the QS's short report against the programme, a list of materials delivered with receipts, photos from the same four corners of the site, and a statement of the project account. Compare spend against the BOQ line by line. If a stage is running over, agree the fix in writing before the next release, not after.
If the builder stops
Stage payments limit how much you can lose, but they do not stop a builder walking away. Keep the contract, the BOQ, every receipt and acknowledgement, and the QS reports in one folder, because they are what a new builder, a lawyer or a court will ask for. Have the QS value the work done to date before anyone else takes over, so you know what you have paid for and what remains. A retention held back and a clear termination clause give you room to bring in someone new without paying twice for the same stage.
Our related guides cover the contract with a Nigerian contractor and a pay-as-you-build cash-flow plan; borrowing against a US home to build is discussed in using a HELOC to build in Nigeria. For the Nigeria-side view, see building a house in Nigeria from abroad.
Where Pryme fits
You can fund a project from dollars with Swap when each stage is approved, and pay the builder's business account by transfer, so every release leaves a record. Ask the builder for a receipt for each payment; you can issue your own verifiable receipt through VerifyDoc.ai that both sides can check.
Questions people ask
How should I pay a builder in Nigeria from abroad?
In stages tied to verified work, with a retention held back, paid to a business account with a receipt each time.
Do I need a quantity surveyor?
It is the most useful independent check. The Quantity Surveyors Act makes it an offence for unregistered people to practise for reward, so check QSRBN registration.
Should I pay for materials in advance?
Avoid large advances. Agree how price changes are handled, or buy major materials yourself with receipts in your name.
What proof should I get before releasing a payment?
A QS report, dated photos and video, materials receipts and a signed acknowledgement of payment.
Sources
- Quantity Surveyors (Registration, etc.) Act (PLAC Laws of Nigeria) · accessed Oct 2026
- FCTA Department of Development Control: Developers' guide, submissions · accessed Oct 2026
- Legit.ng: BUA, Dangote, HBM unveil fresh cement prices (4 Sep 2026) · accessed Oct 2026
This article is general information, not financial, legal or tax advice. Products described are provided under the terms on this site and are subject to regulation and eligibility.