Funding a building project in Nigeria from Australia

Building a house in Nigeria from Australia: staged payments tied to inspections, a registered quantity surveyor, permits, receipts and photo evidence.

The short answer

Pay in stages tied to work you can verify, not in lump sums on request. Have a registered quantity surveyor prepare the bill of quantities and value each stage, pay suppliers and contractors directly against invoices, and ask for dated photos and the stage inspection certificates. In Lagos, buildings need a planning permit and stage certification, and planning permits have been applied for online since April 2026.

"Send the money for the roof" is the most familiar message in diaspora building. Many Nigerians in Australia have stories of a project that took twice as long and cost twice as much because money went out faster than work went up. The fix is a structure where every payment matches something you can check.

Set up the project before the first naira

Permits

In Lagos, the planning permit comes from the Lagos State Physical Planning Permit Authority (LASPPPA), and the Lagos State Building Control Agency (LASBCA) authorises construction and certifies stages such as foundation, damp-proof course, lintel and roofing, then issues a certificate of completion and fitness for habitation, as Ownkey's 2026 permits guide describes. Nairametrics reported that since 1 April 2026 Lagos planning permits are processed only through its online system, which can be used from anywhere. After a building collapse in July 2024, Lagos revoked existing commencement certifications and required owners to revalidate with LASBCA, according to Peoples Gazette. Other states have their own authorities; ask your professionals which apply.

The professionals

  • Architect and structural engineer for drawings and supervision.
  • Quantity surveyor (QS). Under the Quantity Surveyors (Registration, etc.) Act, the Quantity Surveyors Registration Board of Nigeria keeps a register, and it is an offence for an unregistered person to practise as a registered QS for reward. Ask for the QS's registration and check it.
  • Contractor or site manager under a written contract.

The QS prepares a bill of quantities (what materials and work the building needs and their cost) and values each stage before you pay. That valuation is your main control from Australia.

Staged payments

StageEvidence before you release the next payment
Site clearing and setting outDated photos and survey beacons visible
FoundationQS valuation, engineer sign-off, LASBCA stage certificate where applicable
Blockwork to lintelPhotos and video walk-through, QS valuation
RoofingQS valuation, roof photos from several angles, stage certificate
Finishes and servicesItemised invoices for windows, plumbing, electrical; electrical by a certified contractor

Hold back a retention from each payment until the work is finished and defects are fixed. A study of 120 residential projects in Lagos, Ogun, Abuja and Port Harcourt found 5% of project cost to be the most common retention; agree your figure in the contract.

Worked example (illustrative figures)

Example only: the QS values the blockwork stage at ₦9,000,000. With a 5% retention, you pay ₦8,550,000 and hold ₦450,000. Across five stages totalling ₦40,000,000, retention held would be ₦2,000,000, released after the defects period.

Pay suppliers directly

Wherever you can, pay cement, blocks, steel and roofing suppliers directly against their invoices, rather than sending a lump sum to the site manager to buy. Ask suppliers to deliver to site and the site manager to confirm quantities against the delivery note. It closes the gap between what was paid for and what arrived. Keep a running stock list on site, and ask for it with each weekly update, so you can see when materials are being used faster than the work suggests.

Evidence from afar

  • Weekly dated photos and a short video walk-through of the whole site, not close-ups.
  • A visit by someone independent of the contractor once a month.
  • A simple ledger: date, payee, amount, purpose, receipt reference, stage.
  • Copies of permits and stage certificates in one folder.

Contract terms worth insisting on

  1. A fixed scope tied to the approved drawings and the bill of quantities.
  2. A payment schedule by stage, each payment due only after the QS valuation.
  3. A retention percentage and a defects period before it is released.
  4. Who buys materials, and that unused materials belong to you.
  5. A completion date and what happens if it slips.
  6. Named supervision: who signs off each stage for you.

Warning signs

  • Requests for money for a stage that has no photos or valuation yet.
  • Repeated price rises for materials without supplier invoices.
  • Photos that only show close-ups, never the whole building.
  • Pressure to pay a personal account "because the supplier only takes cash".

None of these proves wrongdoing on its own, but each is a reason to pause payment until someone independent visits the site.

Insurance and safety

The Nigerian Insurance Industry Reform Act 2025 includes a builders' liability provision for buildings under construction, covering third-party death, injury and damage and collapse, with building control authorities to check cover before approval, according to Nairametrics' summary. Ask your contractor how this is met.

Where Pryme fits

With naira in a Pryme account you can pay suppliers and contractors directly from Australia with Send, and produce verifiable receipts through VerifyDoc.ai for each payment, so your ledger can be checked later (receipts). Saving towards the next stage in a naira Savings Box keeps it separate (Boxes). For the Nigerian side of building finance, see our guide to building a house in Nigeria from abroad, and before you buy the land, land checks from Australia.

Questions people ask

How do I avoid being cheated building a house in Nigeria from abroad?

Pay in stages against a quantity surveyor's valuation, pay suppliers directly, and require dated photos and stage certificates before each payment.

Do I need a building permit in Lagos?

Yes. LASPPPA issues planning permits, now applied for online, and LASBCA authorises and certifies construction stages.

How do I check a quantity surveyor is registered?

Ask for their registration with the Quantity Surveyors Registration Board of Nigeria; practising as a registered QS without registration is an offence.

What is retention in a building contract?

An amount held back from each payment until the work is complete and defects are fixed; 5% is commonly reported for Nigerian residential projects.

Sources

  1. Ownkey: Nigeria building permits guide 2026 · accessed Oct 2026
  2. Nairametrics: Lagos building approvals now online from anywhere · accessed Oct 2026
  3. Peoples Gazette: Lagos revokes all building permits · accessed Oct 2026
  4. PLAC: Quantity Surveyors (Registration, etc.) Act · accessed Oct 2026
  5. CORE: Retention practices in Nigerian residential building projects · accessed Oct 2026
  6. Nairametrics: Insurance provisions in Nigeria's new Act for developers · accessed Oct 2026